| Title: | 2.4 Notice to Proceed (Exhibit A: Technology Specific Provisions) - Liability Limit |
| Submitted By: | Andrew Lee, Project Developer, Acciona Wind Energy Canada Inc. |
| Date: | 6/26/2009 |
| Document Text: |
For the case of on-shore wind, the draft FIT Contract provides for a pre-construction liability limit of $400,000 + $2000/MW. This is substantially less than the 2% of project costs that what was indicated by the OPA on slide 9 of the Session 5 FIT stakeholder session of April 14, 2009. As an example, using the capital cost assumptions as presented on slide 40 of the Session 4 FIT stakeholder session of April 7, 2009: For a 10 MW project: a) A 2% of project costs pre-construction liability limit would be $640,000 ($3200/kW x 10,000 kW x 2%). b) Under the proposed draft FIT contract, the pre-construction liability limit would be $420,000 ($400,000+$2000/MWx10MW) This corresponds to approximately 1.31% of project costs. For a 100 MW project: As shown, the proposed pre-construction liability limits are considerably less than what was indicated by the OPA during the FIT stakeholder sessions. The 2% of project cost pre-construction liability limit is reasonable and the OPA should set the limit according to the assumptions used in the OPA's pricing models. It is suggested to set the pre-construction liability limits at: Note, the example of on-shore wind is given but a similar methodology should be used for all other technology types as well. This would align with what the OPA had presented during the stakeholder sessions. |