| Title: | Draft Fit Program Rules |
| Submitted By: | d. singer |
| Date: | 7/28/2009 |
| Document Text: |
Submission to the OPA Re: Feedback on the July 10th Draft FIT Program Rules
First, we would like to express our appreciation to the OPA for its efforts in trying to design the FIT Program in a manner that allows "shovel ready" projects to take part. ISSUE: Unfortunately, the current rules as drafted in Section 13 do not allow the True Shovel Ready Projects to participate. The True Shovel Ready Projects cannot give up their connection rights and their RESOP Contract prior to making an application to the FIT Program. Terminating a RESOP Contract and/or a Connection Cost Agreement ("CCA") with Hydro One at anytime during the development and construction of a project will result in an immediate default under any financing agreement that is in place or will put an immediate stop to any financing that is underway. Financing partners will not allow the termination of these agreements for any project in the hope that a FIT Contract is obtained in the future. Furthermore, the Board of Directors of any company that has a True Shovel Ready Project will likely not allow the termination of these agreements due to the significant investments made to become a True Shovel Ready Project. The unintended consequence of Sections 2.1(vii) (RESOP Contract termination) and Section 3.2(b) (CCA termination) of the Draft Fit Program Rules is that they negate the objective of Section 13. That is, to allow and incent the True Shovel Ready Projects to take part in the FIT Program and get to commercial operations as soon as possible. True Shovel Ready Projects that, with a FIT Contract, which by definition could reach commercial operations in a year or less and, as a result, could bid an aggressively high number of COD Acceleration Days, cannot even participate because they will violate or put in jeopardy their financing arrangements and will likely not obtain the approval of their Board of Directors to do so because of the high level of risk it would expose the company to. CHANGE REQUIRED: RECOMMENDATIONS: 1. Incorporate a Two-Tiered Launch Application Process In regards to ranking First Tier Projects, these projects should be able to increase its COD Acceleration Days beyond the limits (725 days) currently provided for in the Draft FIT Program Rules. Further, as First Tier Projects have already purchased wind turbines that were, in most cases, not purchased in Ontario due to component availability, a First Tier Project would not be able to bid the highest number of COD Acceleration Days under the current rules. As a result, the FIT Program Rules should: |