Bioenergy Projects |
|||
| Contract price* | Biomass | ≤ 10 MW | 13.8 ¢/kWh |
| Biomass | > 10 MW | 13.0 ¢/kWh | |
| Biogas on-farm | ≤ 100 kW | 19.5 ¢/kWh | |
| Biogas on-farm | > 100 kW ≤ 250 MW | 18.5 ¢/kWh | |
| Biogas | ≤ 500 kW | 16.0 ¢/kWh | |
| Biogas | > 500 kW ≤ 10 MW | 14.7 ¢/kWh | |
| Biogas | > 10 MW | 10.4 ¢/kWh | |
| Landfill gas | ≤ 10 MW | 11.1 ¢/kWh | |
| > 10 MW | 10.3 ¢/kWh | ||
|
Length of contract |
20 years |
||
|
Percentage escalated |
Ontario Consumer Price Index (CPI) indexation to contract milestone commercial operation date |
||
|
Peak performance factor |
1.35 for all peak hours and 0.90 for all off-peak hours |
||
|
Average lead time |
3 years |
||
|
Contacts for getting connected to provincial grid |
|
||
|
Industry associations and government |
For information on the Green Energy Act, visit the Ministry of Energy and Infrastructure (MEI) For case studies, fact sheets and technical information on biomass, visit the Canadian Bioenergy Association (CANBIO) and the AgriEnergy Producers' Association of Ontario (APAO). For more information on renewable energy generation and conservation on farms, visit the Ontario Ministry of Agriculture, Food and Rural Affairs (OMAFRA). For information on renewable energy approvals, visit the Ministry of the Environment (MOE). |
||
* Eligible for Aboriginal or community adder. For more information regarding eligibility, please refer to the FIT Rules.