| Category: | General - Consultation Process |
| Subject: | Pricing - escalation |
| ID: | 10213 |
| Date: | 4/2/2009 |
| Question: | What percentage of the Contract Price will be linked to the CPI? |
| Answer: | For projects other than PV, the draft FIT schedule proposes that 20% of the Contract Price would be indexed to CPI. |