Q&A Tool

Category:  Micro-Generator - General
Subject:  microfit projects and REA
ID:  10728
Date:  9/8/2009
Question:  In regards to the draft rules for the microFIT program, Section 2 - Project Eligibility Requirements

2.1 e) What would be the test to determine when a microFIT project would require a renewable energy approval from the MOE?

JStory
OSEA
 

Answer:  The Ministry of the Environment and the Ministry of Natural Resources are establishing the rules for Renewable Energy Approvals. These rules are in draft form and can be found:

http://www.ebr.gov.on.ca/ERS-WEB-External/displaynoticecontent.do?notice...

Based on the above, solar PV 10 kW or less do not require an REA. Wind power greater than 3 kW will require an REA.