| Category: | Other |
| Subject: | SES 4: Connection costs |
| ID: | 10333 |
| Date: | 4/15/2009 |
| Question: | Regarding Connection Costs (slide 22), were CCE/CCRA quotes given by LDC's taken into consideration? |
| Answer: | Connection costs were an element of the underlying capital cost estimates. CCE/CCRA quotes from LDCs which could be appropriate for distribution connected projects weren't considered. |