| Category: | Solar - Eligibility Criteria |
| Subject: | Solar < 250 kW |
| ID: | 10752 |
| Date: | 9/10/2009 |
| Question: | As I understand the rules, a PV system under 250 kW is exempt from the Application Security requirments. Are these same systems exempt from the Completion and Performance Security as well? |
| Answer: | All projects (> 10kW) will be required to submit completion and performance security. |