| Category: | Bio-Energy - General |
| Subject: | Off-farm AD |
| ID: | 10583 |
| Date: | 7/17/2009 |
| Question: | In the revised Draft Price Schedule dated July 8, there is only an indication for FiT contract pricing specified for On-Farm operations (is this a Type-o?). Will the FiT still be including Off-Farm projects? If so, will the pricing be the same? |
| Answer: |
The new prices for on farm biogas projects are not meant to replace the non-farm projects "C the on farm prices are an addition to the original prices. This means that non farm biogas projects are still eligible for:
¡Ü 500 kW " 16.0cents/kWh
|