Q&A Tool

Category:  Bio-Energy - General
Subject:  Off-farm AD
ID:  10583
Date:  7/17/2009
Question:  In the revised Draft Price Schedule dated July 8, there is only an indication for FiT contract pricing specified for On-Farm operations (is this a Type-o?). Will the FiT still be including Off-Farm projects? If so, will the pricing be the same?
Answer:  The new prices for on farm biogas projects are not meant to replace the non-farm projects "C the on farm prices are an addition to the original prices. This means that non farm biogas projects are still eligible for:

¡Ü 500 kW " 16.0cents/kWh
> 500 kW ¡Ü 10 MW " 14.7cents/kWh
> 10 MW " 10.4 cents/kWh

 

Back to Q&A Tool