Below is a list of questions that were submitted electronically to the OPA during the development of the FIT Program. You may click on any question to view the question details and answers.
Please note that these questions and answers were based on the draft FIT Rules. We therefore strongly recommend that you refer to the current FAQs which are based on the final FIT Rules.
| Click headings to sort this list. |
| ID | Category | Subject | Date | Status |
|---|---|---|---|---|
| 10777 | Micro-Generator - General | Refusal to pay for electricity production | 9/23/2009 | Answered |
| 10776 | Solar - Eligibility Criteria | Definition of parking structure | 9/18/2009 | Answered |
| 10775 | General - Consultation Process | Project that uses neighbors meter | 9/18/2009 | Answered |
| 10773 | Solar - Contract Pricing | Current LDC Rules for Net metered Systems | 9/18/2009 | Answered |
| 10772 | Other | 9/15/2009 | Answered | |
| 10771 | Other | ldc CHARGES | 9/16/2009 | Answered |
| 10770 | Other | Application deadline | 9/15/2009 | Answered |
| 10768 | Wind - General | Provencial\Canadian Content | 9/15/2009 | Answered |
| 10767 | Solar - Contract Pricing | Parking lot structure PV mounts | 9/16/2009 | Answered |
| 10766 | Wind - General | 9/15/2009 | Answered | |
| 10765 | Solar - General | Limits on total rooftop solar applications and timelines | 9/16/2009 | Answered |
| 10764 | Other | government agencies | 9/18/2009 | Answered |
| 10763 | Other | Assignment and Change of Control | 9/18/2009 | Answered |
| 10761 | Solar - General | Grants | 9/15/2009 | Answered |
| 10760 | Micro-Generator - General | Solar Micro Gen on Seperate Lan (sub #428) | 9/16/2009 | Answered |
| 10759 | Other | Transmission Maps (submission 427) | 9/15/2009 | Answered |
| 10758 | Micro-Generator - General | Roof Leasing for Solar (submission 426) | 9/15/2009 | Answered |
| 10757 | Solar - Eligibility Criteria | CAE Facilities | 9/16/2009 | Answered |
| 10756 | Solar - General | Proof of access requirement | 9/9/2009 | Pending |
| 10753 | Solar - General | Incremental NTP Security | 9/10/2009 | Answered |
| 10752 | Solar - Eligibility Criteria | Solar < 250 kW | 9/10/2009 | Answered |
| 10751 | Solar - Connection | Embedded Connection kWh Accounting | 9/8/2009 | Answered |
| 10750 | Solar - General | Fit & Microfit | 9/16/2009 | Answered |
| 10749 | Micro-Generator - General | Metering and delays | 9/16/2009 | Answered |
| 10748 | Solar - Eligibility Criteria | 9/16/2009 | Answered | |
| 10747 | Micro-Generator - General | multiple microfit contracts | 9/16/2009 | Answered |
| 10746 | Other | Summary of Security Deposit Rules | 9/15/2009 | Answered |
| 10745 | Wind - Contract Pricing | Indexed Contract Price | 9/2/2009 | Pending |
| 10744 | Other | Transmission Capacity | 9/15/2009 | Answered |
| 10743 | Other | Launch Applications - Projects relying on Bruce to Milton | 9/15/2009 | Answered |
| 10742 | Micro-Generator - General | Alternate Solar Power Micro Gen Site | 9/16/2009 | Answered |
| 10741 | Micro-Generator - General | Submission of Contract | 9/8/2009 | Answered |
| 10740 | Solar - Eligibility Criteria | Existing Generator / System Testing and Commissioning | 9/2/2009 | Answered |
| 10739 | Micro-Generator - General | Undersized generator | 9/4/2009 | Answered |
| 10738 | Other | Personal Net Worth Statements | 9/16/2009 | Answered |
| 10737 | Other | Condominium elegibility | 9/2/2009 | Answered |
| 10736 | Solar - General | Zoning | 9/2/2009 | Answered |
| 10735 | Solar - Connection | Net Meter & microFIT @ the same residence | 9/8/2009 | Answered |
| 10734 | Micro-Generator - General | Where is the Application Document (submission #236) | 8/28/2009 | Answered |
| 10733 | Solar - Contract Pricing | Capital Cost Allowance & Solar Income taxation (submission #345) | 9/9/2009 | Answered |
| 10732 | Micro-Generator - General | Leasing of roofs (submission 384) | 8/28/2009 | Answered |
| 10731 | Solar - Eligibility Criteria | Solar PV installations (submission #294) | 8/28/2009 | Answered |
| 10730 | Other | Capacity Allocation Exemptions (submission 289) | 8/28/2009 | Answered |
| 10729 | Micro-Generator - General | MicroFIT rules regarding municipalities | 9/8/2009 | Answered |
| 10728 | Micro-Generator - General | 9/8/2009 | Answered | |
| 10726 | Other | Upgrades to distribution system | 9/8/2009 | Answered |
| 10725 | Other | Economic connection test | 9/15/2009 | Answered |
| 10724 | Other | Economic connection test | 9/15/2009 | Answered |
| 10723 | Other | Time Stamp process | 9/9/2009 | Answered |
| 10722 | Wind - Contract Pricing | Negative HOEP | 8/28/2009 | Pending |
| 10721 | Wind - Connection | Connection Points | 8/28/2009 | Pending |
| 10720 | Solar - Contract Pricing | Provincial Content Required for Solar PV panels | 9/2/2009 | Answered |
| 10719 | Micro-Generator - General | Microfit ground mount | 9/8/2009 | Answered |
| 10718 | Solar - General | Supplier vs. LDC customer | 9/8/2009 | Answered |
| 10716 | Bio-Energy - General | Failure of LDC to meet Schedule | 8/28/2009 | Answered |
| 10715 | Solar - Contract Pricing | Calculation of Indexed Contract Price | 9/4/2009 | Answered |
| 10714 | Wind - General | Rationale behind lower wind price | 9/9/2009 | Answered |
| 10713 | Other | Difference between Net Metering and FIT | 8/28/2009 | Answered |
| 10711 | Other | Required Zoning | 8/28/2009 | Answered |
| 10710 | Solar - Eligibility Criteria | Provincially affiliated bodies | 8/26/2009 | Answered |
| 10709 | Other | Proponent residency requirements under FIT | 8/28/2009 | Answered |
| 10708 | Other | MicroFIT Contract - CALCULATION OF INDEXED CONTRACT PRICE | 9/4/2009 | Answered |
| 10707 | Micro-Generator - General | MicroFit-Transfer of Contract | 8/27/2009 | Answered |
| 10706 | Micro-Generator - General | Microfit- Proof of ownership or access | 8/27/2009 | Answered |
| 10705 | Solar - Eligibility Criteria | 8/24/2009 | Answered | |
| 10704 | Micro-Generator - General | 10kW definition | 8/27/2009 | Answered |
| 10703 | Micro-Generator - General | 8/27/2009 | Answered | |
| 10702 | Micro-Generator - General | 30 day waiting period - Microfit | 8/28/2009 | Answered |
| 10701 | Micro-Generator - General | Questions for microFIT program | 8/27/2009 | Answered |
| 10700 | Micro-Generator - General | Rept: Micro-Fit Program Rules | 9/4/2009 | Answered |
| 10699 | Micro-Generator - General | Rep: Micro-Fit Program Rules | 8/27/2009 | Answered |
| 10698 | Other | Security Reimbursement for EA failure? | 9/2/2009 | Answered |
| 10697 | Micro-Generator - General | Inverter | 8/27/2009 | Answered |
| 10696 | Other | Transmission Projects | 8/28/2009 | Answered |
| 10695 | Micro-Generator - General | Micro Fit draft rules | 8/27/2009 | Answered |
| 10694 | Other | Connection Point and connection costs | 8/25/2009 | Answered |
| 10693 | Other | Land zoning and taxes (solar) | 8/25/2009 | Answered |
| 10692 | Solar - Eligibility Criteria | 8/27/2009 | Answered | |
| 10691 | Bio-Energy - Contract Pricing | Type of connection | 8/28/2009 | Answered |
| 10690 | Micro-Generator - General | 2 10kw systems, one building, two owners | 8/27/2009 | Answered |
| 10689 | Other | Tangible Net Worth from Equity Provider | 9/17/2009 | Answered |
| 10688 | Micro-Generator - General | microFIT - Supplier vs. LDC customer | 8/24/2009 | Answered |
| 10686 | Other | FIT Launch Period - Similar Experience Criteria | 8/17/2009 | Answered |
| 10685 | Micro-Generator - General | Micro Fit Rules and agreement querstions (various) | 8/24/2009 | Answered |
| 10684 | Micro-Generator - General | Meter owned by LDC, but applicant to ensure smart meter used? (microFIT contract draft Aug 14th) | 9/16/2009 | Answered |
| 10683 | Solar - Contract Pricing | Two 10kW projects on same property | 8/27/2009 | Answered |
| 10682 | Other | Application Security requirements for Capacity Allocation Exempt Projects | 9/7/2009 | Answered |
| 10681 | Solar - Eligibility Criteria | residential rooftops on out buildings | 8/24/2009 | Answered |
| 10679 | Other | Project Financing | 8/18/2009 | Answered |
| 10678 | Wind - Contract Pricing | Wind Turbine Questions (Sub #276) | 8/13/2009 | Answered |
| 10677 | Other | how is the Aboriginal Price Adder is calculated? (Sub #277) | 8/13/2009 | Answered |
| 10676 | Other | Capacity Allocation Exempt Facilities ( C.A.E.F. ) less than or equal to 500 kW on 27.6 kV Feeder | 8/27/2009 | Answered |
| 10675 | Bio-Energy - Contract Pricing | Biogas Pricing - Revised Draft | 8/13/2009 | Answered |
| 10674 | Other | Capacity Allocation Exempt Facility Definition (Sub # 272) | 8/13/2009 | Answered |
| 10673 | Other | 8/26/2009 | Answered | |
| 10671 | Bio-Energy - Contract Pricing | Peak Performance Factor | 9/2/2009 | Answered |
| 10670 | Solar - General | Solar Thermal | 8/24/2009 | Answered |
| 10669 | Solar - Contract Pricing | Preferential pricing for Solar PV installations on Brownfields | 8/24/2009 | Answered |
| 10668 | Solar - Contract Pricing | Ground Solar restrictions | 8/24/2009 | Answered |
| 10667 | Other | Capacity Allocation Exempt Facility | 8/18/2009 | Answered |
| 10665 | Other | Late COD due to the 15 month NTP Response Allowance | 8/17/2009 | Answered |
| 10664 | Solar - Contract Pricing | Adjusting the rate to prime interest rate | 8/14/2009 | Answered |
| 10663 | Solar - Eligibility Criteria | Rooftop Eligibility - Equestrian Riding Arenas | 8/14/2009 | Answered |
| 10662 | Other | Distribution Availability Test (DAT) | 8/17/2009 | Answered |
| 10661 | Other | OPA Discretion to Reject | 8/19/2009 | Answered |
| 10660 | Micro-Generator - General | microFiT Contract on same property as existing RESOP contract | 8/7/2009 | Answered |
| 10659 | Solar - Eligibility Criteria | PV solar arrays | 8/7/2009 | Answered |
| 10658 | Other | Settlement for non-IESO Market Participants and Amendments of the DSC | 8/24/2009 | Answered |
| 10657 | Solar - General | Progress Reports | 8/24/2009 | Answered |
| 10656 | Solar - General | Legality of LDC's Entering into FIT contracts | 8/13/2009 | Answered |
| 10655 | Solar - General | System rating and degradation | 8/24/2009 | Answered |
| 10654 | Solar - Eligibility Criteria | Draft Contract 2.4.b - Financial Plan | 8/24/2009 | Answered |
| 10653 | Solar - Eligibility Criteria | Definition of Rooftop | 8/18/2009 | Answered |
| 10652 | Other | Treatment of Capital Grants | 8/24/2009 | Answered |
| 10651 | Solar - General | 8/18/2009 | Answered | |
| 10650 | Solar - Connection | Connection for Behind the Meter applications | 8/28/2009 | Answered |
| 10649 | Solar - Contract Pricing | Pricing for Behind the Meter applications | 8/28/2009 | Answered |
| 10648 | Wind - Contract Pricing | Contract Price Escalator | 8/18/2009 | Answered |
| 10647 | Solar - Eligibility Criteria | Commercial Operation Date | 8/18/2009 | Answered |
| 10646 | Solar - Eligibility Criteria | Completion and Performance Security Fee? | 8/27/2009 | Answered |
| 10645 | Solar - Eligibility Criteria | SOLAR PV PROJECTS | 8/13/2009 | Answered |
| 10644 | Wind - Contract Pricing | Escalation of Price prior to Contract Execution | 8/18/2009 | Answered |
| 10643 | Micro-Generator - General | Connection and Metering For MicroFIT Projects | 8/13/2009 | Answered |
| 10642 | Bio-Energy - Eligibility Criteria | Fuel Supply | 8/18/2009 | Answered |
| 10641 | Other | late NTP | 8/26/2009 | Answered |
| 10640 | Other | Liquidated Damages for Non-launch and Zero Acceleration projects | 8/26/2009 | Answered |
| 10639 | Other | FIT Rules - COD Acceleration Days | 8/28/2009 | Answered |
| 10638 | Bio-Energy - Connection | CIA | 8/13/2009 | Answered |
| 10637 | Hydroelectric - General | re - Re-built generating facilities and FIT rules | 7/27/2009 | Answered |
| 10636 | Solar - Eligibility Criteria | Provincial Content | 8/7/2009 | Answered |
| 10635 | Solar - General | What is involved in expanding your pv project? | 8/4/2009 | Answered |
| 10634 | Solar - Eligibility Criteria | Shovel readiness and equipment availability | 8/13/2009 | Answered |
| 10633 | Other | Micro Fit Program | 8/4/2009 | Answered |
| 10632 | Other | After The FIT Contract Expires | 8/24/2009 | Answered |
| 10631 | Other | Metering Hybrid Generation Site | 8/4/2009 | Answered |
| 10630 | Other | Connection details - transmission circuit | 8/4/2009 | Answered |
| 10629 | General - Consultation Process | Connection details - breaker requirements | 8/4/2009 | Answered |
| 10628 | Solar - General | Does Contract Default Date Shrink with COD Acceleration? | 8/4/2009 | Answered |
| 10626 | Wind - Eligibility Criteria | Offshore Wind | 8/4/2009 | Answered |
| 10625 | Solar - Eligibility Criteria | 10kW Micro-FIT limit | 8/13/2009 | Answered |
| 10624 | Solar - Eligibility Criteria | Rooftop definition | 8/13/2009 | Answered |
| 10623 | Solar - Eligibility Criteria | microFIT Program - Section 2.1(a)(iii) | 8/4/2009 | Answered |
| 10622 | Hydroelectric - Eligibility Criteria | Access Rights on Prov Crown Land - Waterpower | 8/13/2009 | Answered |
| 10621 | Hydroelectric - General | Major Equipment Component - Waterpower | 7/31/2009 | Answered |
| 10620 | Other | 7/31/2009 | Answered | |
| 10619 | Other | Completion and Performanc Security | 8/4/2009 | Answered |
| 10618 | Bio-Energy - Contract Pricing | Fuel supply escalator | 7/31/2009 | Answered |
| 10617 | Other | Launch date for TAPS Tool | 7/31/2009 | Answered |
| 10616 | General - Consultation Process | Registered Facility | 8/7/2009 | Answered |
| 10615 | Hydroelectric - General | New or Incremental Hydroelectric Development | 7/31/2009 | Answered |
| 10614 | Solar - General | System "nameplate rating" | 8/13/2009 | Answered |
| 10613 | Other | Successful Experience with Similar Facility | 7/31/2009 | Answered |
| 10612 | Solar - Eligibility Criteria | Multi-site Solar Power | 7/31/2009 | Answered |
| 10609 | Solar - Connection | Distrbution feeder connection 15kv | 7/31/2009 | Answered |
| 10608 | Solar - General | PV - Nameplate rating | 8/13/2009 | Answered |
| 10607 | Solar - Eligibility Criteria | No Requirement for Proof of Product Before Applying | 8/24/2009 | Answered |
| 10606 | Solar - Eligibility Criteria | Launch criteria | 7/31/2009 | Answered |
| 10605 | Solar - Eligibility Criteria | Provincial Content size limits | 7/31/2009 | Answered |
| 10604 | Solar - Contract Pricing | Why subsidize Solar? | 7/31/2009 | Answered |
| 10603 | Solar - Connection | Connection Application | 7/31/2009 | Answered |
| 10602 | General - Consultation Process | Historic CIA holding FIT capacity hostage | 7/31/2009 | Answered |
| 10601 | Wind - General | Crown Land | 7/31/2009 | Answered |
| 10600 | Micro-Generator - General | Toronto Hydro and Micro Fit | 7/28/2009 | Answered |
| 10599 | Micro-Generator - General | Solar PV and Provincial Content | 7/31/2009 | Answered |
| 10598 | Solar - Connection | Net Metering/FIT Program | 8/4/2009 | Answered |
| 10597 | Solar - General | Provision 3.2 in the the new draft rules | 7/31/2009 | Answered |
| 10596 | Other | Rural Area Grid Connection | 7/31/2009 | Answered |
| 10595 | Solar - Contract Pricing | Escalation Percentage for Solar PV projects | 8/4/2009 | Answered |
| 10594 | Other | residential installations | 8/4/2009 | Answered |
| 10593 | Other | Behind the grind connection | 7/31/2009 | Answered |
| 10592 | Solar - General | Ontario Building Code 2006/FIT for Solar PV rooftop | 8/4/2009 | Answered |
| 10591 | General - Consultation Process | FIT Contract Exhibits - Draft June 8, 2009 | 8/13/2009 | Answered |
| 10590 | Solar - General | Gross Nameplate Definitions | 8/13/2009 | Answered |
| 10589 | Other | COD Acceleration Days | 8/11/2009 | Answered |
| 10588 | General - Consultation Process | 8/11/2009 | Answered | |
| 10587 | General - Consultation Process | Community clarification | 7/17/2009 | Answered |
| 10586 | General - Consultation Process | The rated capacity and the amount I will use for my own home | 8/11/2009 | Answered |
| 10585 | General - Consultation Process | New FIT Rules- Legacy Projects | 8/11/2009 | Answered |
| 10584 | General - Consultation Process | FIT Rules Eligibility Requirements | 7/27/2009 | Answered |
| 10583 | Bio-Energy - General | Off-farm AD | 7/17/2009 | Answered |
| 10582 | Bio-Energy - Contract Pricing | escalation percentage | 9/9/2009 | Answered |
| 10581 | General - Consultation Process | Contract timing summaries | 7/17/2009 | Answered |
| 10580 | Other | Magnetic Generator, acceptation and rate | 7/17/2009 | Answered |
| 10579 | Solar - General | Provincial Content | 7/17/2009 | Answered |
| 10578 | Micro-Generator - General | Home REFIT Program: When we can expect it? | 7/17/2009 | Answered |
| 10577 | Bio-Energy - Eligibility Criteria | Treated wood waste | 8/12/2009 | Answered |
| 10576 | Solar - General | income tax solar <10kw | 7/17/2009 | Answered |
| 10575 | Solar - General | transmission charges | 8/13/2009 | Answered |
| 10574 | Solar - Contract Pricing | Clarification of solar array mounting | 7/17/2009 | Answered |
| 10573 | General - Consultation Process | Micro FIT | 7/17/2009 | Answered |
| 10572 | Wind - General | NTP Response Date | 8/13/2009 | Answered |
| 10571 | Other | Eastern Orange Zone | 7/31/2009 | Answered |
| 10570 | Solar - General | Proposed Solar PV Feed in Tariff Program: | 8/13/2009 | Answered |
| 10569 | Solar - General | PV System power rating | 7/17/2009 | Answered |
| 10568 | Wind - General | Letters of Intent | 7/31/2009 | Answered |
| 10567 | General - Consultation Process | Request NTP | 8/12/2009 | Answered |
| 10566 | General - Consultation Process | What is an Automatic NTP facility? | 8/12/2009 | Answered |
| 10565 | Wind - General | NTP - Conditional on Financial Plan? | 8/12/2009 | Answered |
| 10564 | Wind - General | Leaving FIT Reserve | 7/31/2009 | Answered |
| 10563 | General - Consultation Process | FIT Contract -Draft June 8th, 2009 | 7/31/2009 | Answered |
| 10562 | General - Consultation Process | PV name plate rating | 7/17/2009 | Answered |
| 10561 | Wind - General | Repermitting new turbines | 8/12/2009 | Answered |
| 10560 | Solar - General | Single owner eligible for payment from multi-site solar installations | 7/8/2009 | Answered |
| 10559 | Solar - General | Solar Array on abutting property | 7/8/2009 | Answered |
| 10557 | Micro-Generator - General | 2 properties | 7/8/2009 | Answered |
| 10556 | Solar - Eligibility Criteria | Can I go ahead and connect my solar PV panels now? | 7/7/2009 | Answered |
| 10555 | General - Consultation Process | Home PV calculation | 8/13/2009 | Answered |
| 10554 | Other | Duration of FIT Program | 8/13/2009 | Answered |
| 10553 | Solar - Connection | CIA Submission | 7/17/2009 | Answered |
| 10552 | Other | Contract Appendices - Form of Lender Consent | 8/14/2009 | Answered |
| 10551 | Other | Contract Appendices - Form of Confidentiality Agreement | 8/14/2009 | Answered |
| 10550 | Wind - General | Application Security $10,000 for wind? | 8/14/2009 | Answered |
| 10548 | Solar - General | GST and PST charges on Solar PV panels and ancillary equipment | 7/17/2009 | Answered |
| 10547 | Other | CCRA | 8/13/2009 | Answered |
| 10545 | Solar - Eligibility Criteria | 7/17/2009 | Answered | |
| 10544 | Solar - Eligibility Criteria | CRD | 6/30/2009 | Answered |
| 10543 | Solar - Connection | Connection costs | 7/7/2009 | Answered |
| 10542 | Other | Eco Energy | 7/17/2009 | Answered |
| 10541 | Solar - Eligibility Criteria | Interpretation of Section G: Proposed Renewable Energy Approval | 7/7/2009 | Answered |
| 10540 | Solar - Connection | Behind Meter | 7/17/2009 | Answered |
| 10539 | Solar - Connection | Solar PV | 7/7/2009 | Answered |
| 10538 | Wind - General | Demonstrated location access requirements | 8/24/2009 | Answered |
| 10537 | Wind - Connection | Voltage requirements | 8/14/2009 | Answered |
| 10536 | Wind - General | FIT financial backing | 7/17/2009 | Answered |
| 10535 | Wind - Connection | Interconnection process | 7/17/2009 | Answered |
| 10534 | Solar - General | 7/7/2009 | Answered | |
| 10533 | Solar - Contract Pricing | Pricing for Ground PV Installations | 7/7/2009 | Answered |
| 10531 | Solar - Contract Pricing | The 50% to be paid to OPA | 6/29/2009 | Answered |
| 10530 | Solar - General | Solar Tracking | 6/29/2009 | Answered |
| 10529 | Solar - Connection | how do we determine capacity at a given location | 6/29/2009 | Answered |
| 10528 | Micro-Generator - General | <10 kW Pricing for Ground Mounted PV | 6/29/2009 | Answered |
| 10527 | Other | Gross or Net? | 8/13/2009 | Answered |
| 10526 | Other | MicroFit | 6/29/2009 | Answered |
| 10525 | Other | Draft Contract of June 08 | 6/29/2009 | Answered |
| 10524 | Wind - Eligibility Criteria | Smallest Size | 6/29/2009 | Answered |
| 10523 | Micro-Generator - General | Where do we fill out the Micro FIT application? | 6/29/2009 | Answered |
| 10522 | Solar - General | Connection Resource Database | 6/30/2009 | Answered |
| 10521 | Solar - General | The 10kw to 50kw solar system | 6/29/2009 | Answered |
| 10520 | Solar - Connection | Mico-Generator Connection costs | 6/29/2009 | Answered |
| 10519 | Solar - Connection | Queue Exempt and LDC Preferences | 8/13/2009 | Answered |
| 10518 | Other | change of control provisions | 8/13/2009 | Answered |
| 10517 | General - Consultation Process | Legacy Projects- Next Steps | 6/29/2009 | Answered |
| 10516 | Solar - Contract Pricing | Capacity Overproduction & Improvements | 6/18/2009 | Answered |
| 10515 | Solar - Eligibility Criteria | Small Multi-unit Commercial | 6/29/2009 | Answered |
| 10512 | Other | Existing Completely Redeveloped generating station | 6/9/2009 | Answered |
| 10511 | Solar - General | Settlement | 6/9/2009 | Answered |
| 10510 | Micro-Generator - General | Low interest loans | 8/13/2009 | Answered |
| 10508 | Solar - Eligibility Criteria | Solar Technology | 6/22/2009 | Answered |
| 10507 | Solar - Eligibility Criteria | Leasing roof space | 8/13/2009 | Answered |
| 10505 | General - Consultation Process | Beginning of Initialization Period - Queue Positions | 6/9/2009 | Answered |
| 10502 | Hydroelectric - General | Redeveloped generating station | 5/26/2009 | Answered |
| 10501 | Solar - Eligibility Criteria | Wall Mounted Panels | 6/9/2009 | Answered |
| 10499 | Bio-Energy - Eligibility Criteria | Biomass Gasification | 8/13/2009 | Answered |
| 10498 | Micro-Generator - General | SES 8: Timeline for approval (#1257) | 5/25/2009 | Answered |
| 10497 | Wind - Contract Pricing | 5/25/2009 | Answered | |
| 10496 | Solar - Connection | Changes in Distribution System Code | 6/3/2009 | Answered |
| 10495 | General - Consultation Process | Future Performance Security | 6/29/2009 | Answered |
| 10494 | Other | Curtailment | 8/13/2009 | Answered |
| 10493 | Wind - Eligibility Criteria | wind data requirement clarification | 8/13/2009 | Answered |
| 10492 | General - Consultation Process | Draft FIT Contract | 6/3/2009 | Answered |
| 10491 | Solar - General | Calculation of potential revenue from a solar install | 5/29/2009 | Answered |
| 10489 | Solar - Contract Pricing | Nameplate rating or true output | 5/29/2009 | Answered |
| 10488 | Solar - General | Solar PV on rooftop on buildings before 2006, different building code | 5/29/2009 | Answered |
| 10487 | General - Consultation Process | Draft Contract FIT | 6/9/2009 | Answered |
| 10486 | Solar - General | Solar panels mounted on parking lot canopies/definition | 5/29/2009 | Answered |
| 10485 | General - Consultation Process | Multiple rooftop PV projects on one rooftop | 6/8/2009 | Answered |
| 10484 | Solar - Eligibility Criteria | RESOP to FIT | 6/8/2009 | Answered |
| 10483 | Wind - Contract Pricing | Small wind | 5/26/2009 | Answered |
| 10482 | Micro-Generator - General | transferring contract | 5/25/2009 | Answered |
| 10481 | General - Consultation Process | Green Energy Act | 5/25/2009 | Answered |
| 10480 | Micro-Generator - General | Cost for Residential homes to enter the FIT program | 5/25/2009 | Answered |
| 10478 | Wind - Eligibility Criteria | Group I Project | 8/13/2009 | Answered |
| 10477 | Hydroelectric - Contract Pricing | revised draft pricing options | 5/25/2009 | Answered |
| 10474 | Wind - Contract Pricing | Capacity Factor Wind | 5/25/2009 | Answered |
| 10473 | General - Consultation Process | Community Group DEFINITION | 5/25/2009 | Answered |
| 10472 | Wind - Contract Pricing | Northern Ontario costs for wind projects | 5/25/2009 | Answered |
| 10471 | Wind - Connection | TAT Availability | 5/25/2009 | Answered |
| 10469 | Solar - Contract Pricing | SES 8: Solar pricing (1247) | 5/25/2009 | Answered |
| 10468 | Micro-Generator - General | combined technologies re: Question ID 10444 | 6/22/2009 | Answered |
| 10467 | Solar - Eligibility Criteria | Roof Photovoltaics | 5/25/2009 | Answered |
| 10466 | Solar - General | Definition of Rooftop / Pricing clarity | 5/25/2009 | Answered |
| 10465 | Solar - Eligibility Criteria | Multiple Rooftop Installations | 7/8/2009 | Answered |
| 10463 | Solar - Connection | Queue Exempt Facilities | 6/18/2009 | Answered |
| 10462 | Other | Performance Bond Risk (Sub #186) | 8/24/2009 | Answered |
| 10461 | Solar - General | Home REFIT Program | 5/25/2009 | Answered |
| 10460 | Solar - General | RESOP & FIT together | 5/5/2009 | Answered |
| 10459 | General - Consultation Process | Metis Definition | 7/7/2009 | Answered |
| 10457 | Solar - General | Timeline of FIT program | 5/5/2009 | Answered |
| 10456 | Solar - Contract Pricing | Pricing Schedule | 5/5/2009 | Answered |
| 10455 | Solar - General | Roof top photovoltaics | 5/5/2009 | Answered |
| 10453 | Other | Application Security | 8/24/2009 | Answered |
| 10452 | General - Consultation Process | First Nations Projects | 6/18/2009 | Answered |
| 10451 | General - Consultation Process | Residential solar array expansion | 5/5/2009 | Answered |
| 10449 | Solar - General | Calculation of Residential Generation Facility | 5/5/2009 | Answered |
| 10448 | Micro-Generator - General | 5/5/2009 | Answered | |
| 10447 | Other | Community Project - condominium? (Sub #158) | 4/25/2009 | Answered |
| 10446 | Other | Foreign Ownership & Financing | 4/25/2009 | Answered |
| 10445 | Other | legal regulations for holding the interest | 4/25/2009 | Answered |
| 10444 | Micro-Generator - General | combined technologies | 5/5/2009 | Answered |
| 10441 | Wind - Eligibility Criteria | Legacy Transmission Project Evalution criteria | 5/26/2009 | Answered |
| 10440 | Solar - Eligibility Criteria | Eligibility of Provincially Owned Corporations | 5/5/2009 | Answered |
| 10439 | Solar - Contract Pricing | Further Details re: Navigant Assumption | 5/5/2009 | Answered |
| 10438 | Other | Section 4.3(c) (Sub. #160) | 4/21/2009 | Answered |
| 10437 | Other | CIA (Sub. #161) | 4/21/2009 | Answered |
| 10436 | Solar - Contract Pricing | Non PV solar projects... stirling dishes... FIT pricing ? | 5/5/2009 | Answered |
| 10435 | Other | SES 6: 80% transformer limit (#1075) | 5/4/2009 | Answered |
| 10434 | Other | SES 6: RESOP & reserved transmission (#1073) | 4/25/2009 | Answered |
| 10433 | Other | SES 6: Slide 7 (#1076) | 4/25/2009 | Answered |
| 10432 | Other | SES 6: Projects below red line (#1072) | 4/25/2009 | Answered |
| 10430 | Wind - Connection | Northern Ontario and Prosperity | 4/25/2009 | Answered |
| 10429 | Other | Northern Ontario Heritage Fund/pricing | 4/25/2009 | Answered |
| 10428 | Solar - Contract Pricing | Tariff prices for many systems of less than 10 kW | 4/25/2009 | Answered |
| 10425 | Other | Dispatchable Power | 4/25/2009 | Answered |
| 10424 | Solar - Contract Pricing | 'take or pay' clause | 4/20/2009 | Answered |
| 10423 | Wind - Connection | Interconnection Costs | 4/25/2009 | Answered |
| 10421 | Wind - Contract Pricing | Pricing Escalation for Wind | 4/20/2009 | Answered |
| 10420 | Solar - Eligibility Criteria | Technology other that Solar PV | 4/20/2009 | Answered |
| 10419 | Hydroelectric - Eligibility Criteria | Marine Current Technology | 4/21/2009 | Answered |
| 10418 | Micro-Generator - General | Application Process - Less than 10kW | 4/21/2009 | Answered |
| 10417 | Other | Southwest Region | 4/21/2009 | Answered |
| 10416 | Wind - Connection | MET Tower | 4/21/2009 | Answered |
| 10415 | Other | Initialization period | 4/25/2009 | Answered |
| 10414 | Solar - Contract Pricing | Solar PV - Project Sizing Definition | 4/25/2009 | Answered |
| 10412 | Solar - Eligibility Criteria | Quebec Power supplied to Ontario residents- are they eligible | 4/21/2009 | Answered |
| 10411 | Wind - General | MET Tower | 4/21/2009 | Answered |
| 10410 | Other | Information in Connection Resource Database | 4/25/2009 | Answered |
| 10409 | Other | Requirements for Wind and Water Applications | 4/21/2009 | Answered |
| 10408 | Solar - General | security deposits | 4/20/2009 | Answered |
| 10407 | General - Consultation Process | OPA administrative process | 4/20/2009 | Answered |
| 10406 | Other | Energy from Waste | 4/21/2009 | Answered |
| 10405 | Wind - Eligibility Criteria | SES 2: MNR and Applicant of Record | 4/14/2009 | Answered |
| 10404 | Other | Initial Fit Application Activity | 4/14/2009 | Answered |
| 10403 | Other | Legacy Projects - Definition | 4/14/2009 | Answered |
| 10402 | Solar - Eligibility Criteria | Options and Offer to Purchase agreement expiration dates. | 4/25/2009 | Answered |
| 10401 | Other | SES 5: Slide 28 Definition of Related Products | 5/5/2009 | Answered |
| 10399 | Bio-Energy - General | SES 5: Related products | 5/25/2009 | Answered |
| 10398 | Other | SES 5: HOEP | 4/21/2009 | Answered |
| 10397 | Other | SES 5: Security interest | 6/18/2009 | Answered |
| 10396 | Other | SES 5: HOEP greater than FIT | 4/21/2009 | Answered |
| 10395 | Other | SES 5: Slide 19 Interest | 4/25/2009 | Answered |
| 10394 | Other | SES 5: Slide 19 - HOEP | 4/25/2009 | Answered |
| 10393 | Other | Definition of Access | 4/25/2009 | Answered |
| 10392 | Other | SES 5: NTP Security | 4/25/2009 | Answered |
| 10391 | Other | SES 5: Force Majeure due to federal approval | 4/21/2009 | Answered |
| 10390 | Other | Application process (Submission #100) | 4/21/2009 | Answered |
| 10389 | Other | 4/25/2009 | Answered | |
| 10388 | Other | Queue Exempt Facility - phase projects | 4/25/2009 | Answered |
| 10387 | Other | SES 5: Map of grid access points | 4/20/2009 | Answered |
| 10386 | Other | SES 5: Secured lender | 4/25/2009 | Answered |
| 10385 | Solar - Contract Pricing | SES 5: Grouping projects | 4/15/2009 | Answered |
| 10383 | Hydroelectric - Contract Pricing | SES 4: Cost of rental charges | 5/5/2009 | Answered |
| 10382 | Other | Financial commitment documentation for Notice-To-Proceed application | 4/25/2009 | Answered |
| 10381 | Solar - Contract Pricing | Using Generated Electricty On Site & FIT (Submission 102) | 4/15/2009 | Answered |
| 10378 | Solar - General | Financial feasibility of rooftop PV systems | 4/15/2009 | Answered |
| 10377 | General - Consultation Process | 4/21/2009 | Answered | |
| 10376 | Solar - Contract Pricing | Contract Pricing - Change in PV technology | 4/21/2009 | Answered |
| 10375 | General - Consultation Process | Multiple projects | 4/21/2009 | Answered |
| 10374 | Wind - Eligibility Criteria | Use of remote sensing equipment | 4/21/2009 | Answered |
| 10373 | General - Consultation Process | Difference between Online Q&A and Submission | 4/14/2009 | Answered |
| 10370 | Solar - Eligibility Criteria | Made in Canada | 4/21/2009 | Answered |
| 10369 | Solar - General | After 20 years | 4/13/2009 | Answered |
| 10366 | Other | yellow/orange zone | 4/21/2009 | Answered |
| 10365 | Wind - Contract Pricing | 10 mgw wind | 4/13/2009 | Answered |
| 10364 | Solar - General | General/Historical Rates (SUB#62) | 4/8/2009 | Answered |
| 10361 | Wind - Eligibility Criteria | Trained Meteorologist | 4/14/2009 | Answered |
| 10359 | Solar - Contract Pricing | location vs. size of installation | 4/14/2009 | Answered |
| 10358 | Other | SES 4: Global Adjustment | 4/11/2009 | Answered |
| 10357 | Other | SES 4: 20 year contract | 4/8/2009 | Answered |
| 10356 | Solar - Eligibility Criteria | Metering & Settlement | 6/3/2009 | Answered |
| 10355 | Hydroelectric - Contract Pricing | Community/Aboriginal Pricing | 4/8/2009 | Answered |
| 10354 | Solar - Contract Pricing | SES 4: Which model number | 4/8/2009 | Answered |
| 10353 | Solar - Contract Pricing | SES 4: Canadian sources | 4/8/2009 | Answered |
| 10351 | Other | SES 4: Exchange rate | 6/9/2009 | Answered |
| 10350 | Bio-Energy - General | SES 4: CHP | 4/14/2009 | Answered |
| 10349 | Other | SES 4: CapEx assumptions | 5/29/2009 | Answered |
| 10348 | Other | SES 4: Summary package | 4/11/2009 | Answered |
| 10347 | Bio-Energy - Contract Pricing | SES 4: Full price | 4/8/2009 | Answered |
| 10346 | General - Consultation Process | Application review and exceptance | 4/20/2009 | Answered |
| 10345 | Other | SES 4: Global Adjustment | 4/14/2009 | Answered |
| 10344 | Wind - Contract Pricing | SES 4: Wind - peaking price | 4/8/2009 | Answered |
| 10343 | Other | FIT Pricing | 4/13/2009 | Answered |
| 10342 | Micro-Generator - General | SES 4: Definition of rooftop | 4/8/2009 | Answered |
| 10341 | Solar - Contract Pricing | SES 4: Degression | 4/8/2009 | Answered |
| 10339 | Other | SES 4: Aboriginal Projects | 4/11/2009 | Answered |
| 10338 | Other | SES 4: Standard connection cost assumption | 4/11/2009 | Answered |
| 10337 | Bio-Energy - Contract Pricing | SES 4: OPG and biomass initiative | 4/14/2009 | Answered |
| 10336 | Solar - Contract Pricing | SES 4: OEB's microscale embedded generation | 4/11/2009 | Answered |
| 10335 | Other | SES 4: Review for unusual increases | 4/7/2009 | Answered |
| 10334 | Hydroelectric - Contract Pricing | Session 4 Aboriginal Pricing | 4/8/2009 | Answered |
| 10333 | Other | SES 4: Connection costs | 4/15/2009 | Answered |
| 10332 | Bio-Energy - Contract Pricing | SES 4: Heat & Power approach | 4/11/2009 | Answered |
| 10331 | Wind - Contract Pricing | SES 4: Capacity factor for wind | 4/7/2009 | Answered |
| 10330 | Other | SES 4: Community Based Technologies | 4/11/2009 | Answered |
| 10329 | Solar - Contract Pricing | SES 4: RESOP contract holder | 4/11/2009 | Answered |
| 10328 | Other | SES 4: Assumptions with debt | 4/15/2009 | Answered |
| 10327 | Other | SES 4: Concentrated Solar | 4/11/2009 | Answered |
| 10326 | Other | SES 4: Pricing and economic factors | 4/13/2009 | Answered |
| 10325 | Solar - Contract Pricing | SES 4: 2 year review period | 4/8/2009 | Answered |
| 10324 | Solar - Contract Pricing | SES 4: Decrease in technology costs | 4/8/2009 | Answered |
| 10323 | Solar - Contract Pricing | SES 4: 9% degression | 4/8/2009 | Answered |
| 10322 | Wind - Eligibility Criteria | Legacy Project Eligibility | 4/21/2009 | Answered |
| 10321 | General - Consultation Process | NTD | 4/11/2009 | Answered |
| 10320 | General - Consultation Process | Waterpower - requirement for 10 years correlated data | 6/8/2009 | Answered |
| 10319 | General - Consultation Process | FIT for solar PV installations | 4/11/2009 | Answered |
| 10318 | Solar - General | Micro Fit - Sale of Home & Contract | 5/29/2009 | Answered |
| 10317 | Other | Fees (SUB#60) | 4/6/2009 | Answered |
| 10316 | Hydroelectric - Contract Pricing | Provisions for renewable energy former non-utility Generators ? | 4/22/2009 | Answered |
| 10315 | General - Consultation Process | Renewable Energy Project Permitting | 4/11/2009 | Answered |
| 10314 | General - Consultation Process | Project Site to Grid Connection Costs | 4/7/2009 | Answered |
| 10313 | General - Consultation Process | Transmission Capacity | 4/11/2009 | Answered |
| 10312 | General - Consultation Process | FIT Rates | 4/7/2009 | Answered |
| 10311 | Micro-Generator - General | Project Cost and Return on Investment | 4/13/2009 | Answered |
| 10310 | Micro-Generator - General | Small Business 1-10kv and 10-50kv Renewable Projects | 4/7/2009 | Answered |
| 10308 | Solar - Contract Pricing | Micro-solar | 4/8/2009 | Answered |
| 10307 | Solar - Contract Pricing | 4/13/2009 | Answered | |
| 10306 | General - Consultation Process | Ses 4 Proposed Feed-in Prices | 6/9/2009 | Answered |
| 10305 | General - Consultation Process | Solar, wind and batteries | 5/26/2009 | Answered |
| 10304 | Solar - Contract Pricing | SES 2: Price Degression | 4/3/2009 | Answered |
| 10303 | Other | Early Movers (SUB#30) | 4/3/2009 | Answered |
| 10302 | Other | Micro CHP (SUB#26) | 4/3/2009 | Answered |
| 10301 | Solar - General | Solar Building Integrated (SUB#20) | 4/3/2009 | Answered |
| 10300 | General - Consultation Process | Application Ready? (SUB#38) | 4/3/2009 | Answered |
| 10299 | General - Consultation Process | Connection Alteration Proposal (SUB#46) | 4/3/2009 | Answered |
| 10298 | Bio-Energy - Contract Pricing | Incremental Project - Existing Facility Capacity | 4/8/2009 | Answered |
| 10297 | Other | RESOP Applications (SUB #21) | 4/11/2009 | Answered |
| 10296 | Other | SES 2: Economic Connection Test & future developments | 4/2/2009 | Answered |
| 10295 | Solar - Contract Pricing | Tranche Sizes | 4/21/2009 | Answered |
| 10294 | Other | Behind the Meter Settlement | 4/15/2009 | Answered |
| 10293 | Solar - General | Do queue exempt facilities have to provide a performance and completion security? | 4/11/2009 | Answered |
| 10292 | Other | Legacy Projects | 4/7/2009 | Answered |
| 10291 | Other | Completion Security (SUB#50) | 4/2/2009 | Answered |
| 10290 | Other | Geothermal (SUB#44) | 4/2/2009 | Answered |
| 10289 | Other | COMMISSIONING & ELIGIBILITY (SUB#40) | 4/2/2009 | Answered |
| 10288 | Solar - General | Solar Questions (SUB#10) | 4/2/2009 | Answered |
| 10287 | Bio-Energy - General | Geothermal Energy (SUB#12) | 4/2/2009 | Answered |
| 10286 | Other | Legacy Project | 4/7/2009 | Answered |
| 10285 | Other | New application (SUB#8) | 8/13/2009 | Answered |
| 10284 | Solar - Contract Pricing | Groundmount Pricing - 10-100kW and 100-500kW | 4/8/2009 | Answered |
| 10282 | General - Consultation Process | Small wind turbines inside cities | 4/3/2009 | Answered |
| 10281 | General - Consultation Process | certification of small wind turbines and inverters | 4/8/2009 | Answered |
| 10280 | General - Consultation Process | Small wind turbines in cities | 4/3/2009 | Answered |
| 10279 | General - Consultation Process | zoning for small wind turbines <3 Kw | 4/8/2009 | Answered |
| 10275 | Solar - Eligibility Criteria | Solar Rooftops < 500Kw Exempt from Security Fee? | 4/2/2009 | Answered |
| 10274 | Solar - Contract Pricing | Justification for buying electricity at 80.2 cents | 4/15/2009 | Answered |
| 10273 | Wind - General | Resource Assessment Planning | 4/8/2009 | Answered |
| 10272 | General - Consultation Process | RESOP price differentials | 4/3/2009 | Answered |
| 10270 | General - Consultation Process | Legacy Projects | 4/3/2009 | Answered |
| 10268 | General - Consultation Process | Application Submittal (legacy projects) | 4/7/2009 | Answered |
| 10267 | Solar - General | PV - low cost financing | 4/1/2009 | Answered |
| 10266 | Other | SES 3: Host under contract with Retailer | 4/2/2009 | Answered |
| 10265 | General - Consultation Process | Consultation with LDCs | 4/2/2009 | Answered |
| 10264 | Other | SES 3: HOEP amount | 4/2/2009 | Answered |
| 10263 | General - Consultation Process | SES 3: Interconnection Process | 4/14/2009 | Answered |
| 10262 | Other | SES 3: Contract for differences | 4/2/2009 | Answered |
| 10261 | Other | 4/2/2009 | Answered | |
| 10260 | Solar - Connection | SES 3: Separate meter requirement | 4/2/2009 | Answered |
| 10259 | Other | SES 3: Splitting NTP into separate deadlines | 4/8/2009 | Answered |
| 10258 | General - Consultation Process | FIT Contract - Funding / CIA / CCE | 4/3/2009 | Answered |
| 10257 | Solar - Contract Pricing | Wall mounted panels | 3/31/2009 | Answered |
| 10256 | Other | SES 3: project timeline variability | 4/15/2009 | Answered |
| 10255 | Other | SES 3: Notice to Proceed and time lines | 4/2/2009 | Answered |
| 10254 | Other | SES 3: Draft application | 4/2/2009 | Answered |
| 10253 | Other | SES 3: Bruce to Milton Upgrade | 4/11/2009 | Answered |
| 10252 | General - Consultation Process | taxes | 4/3/2009 | Answered |
| 10251 | Other | SES 3: Cluster of 6 projects | 4/11/2009 | Answered |
| 10250 | Other | SES 3: 4% project cost | 4/2/2009 | Answered |
| 10249 | Other | SES 3: Areas of planned development | 4/2/2009 | Answered |
| 10248 | Other | SES 3: Category 1 becomes Category 2 | 4/11/2009 | Answered |
| 10247 | Other | SES 3: Category 1 | 4/2/2009 | Answered |
| 10246 | Other | SES 3: Updates on transmission for pre-NTP | 4/2/2009 | Answered |
| 10245 | Hydroelectric - Connection | Zoning | 4/2/2009 | Answered |
| 10244 | General - Consultation Process | Land, Leasing, Options | 4/3/2009 | Answered |
| 10243 | General - Consultation Process | Time Differentiated Pricing | 4/2/2009 | Answered |
| 10242 | General - Consultation Process | Audio File for Consultation Sessions | 4/2/2009 | Answered |
| 10241 | Other | SES 2: Legacy projects and queue position | 3/30/2009 | Answered |
| 10240 | Solar - General | Permanent Brownfield Applications | 9/15/2009 | Answered |
| 10239 | Other | SES 2: School boards and community based projects | 3/31/2009 | Answered |
| 10238 | Solar - Contract Pricing | SES 2: Rationale for price degression | 3/30/2009 | Answered |
| 10237 | Solar - Contract Pricing | SES 2: Price degresssion | 3/30/2009 | Answered |
| 10236 | Solar - General | SES 2: Residential ground mounted panels | 3/30/2009 | Answered |
| 10235 | Other | SES 2: Pricing Worksheets | 3/30/2009 | Answered |
| 10234 | Other | SES 2: Limit on application | 3/30/2009 | Answered |
| 10233 | Other | Connection Point alternatives | 4/15/2009 | Answered |
| 10232 | Wind - General | Transformer Stations identification | 4/21/2009 | Answered |
| 10231 | Wind - Eligibility Criteria | Met Tower location 5 km | 4/2/2009 | Answered |
| 10230 | Micro-Generator - General | Home refit program | 4/1/2009 | Answered |
| 10229 | Wind - Eligibility Criteria | Subsidies | 4/2/2009 | Answered |
| 10228 | Wind - Connection | Northern Ontario | 4/2/2009 | Answered |
| 10226 | Other | Land lease/ownership requirement | 4/15/2009 | Answered |
| 10224 | Hydroelectric - General | Northern Hydroelectric Initiative | 5/5/2009 | Answered |
| 10223 | General - Consultation Process | Execution of | 4/8/2009 | Answered |
| 10221 | Solar - Contract Pricing | CPI for solar | 4/2/2009 | Answered |
| 10220 | Wind - Eligibility Criteria | Legacy status - CIA submitted but not completed | 4/1/2009 | Answered |
| 10219 | Hydroelectric - Eligibility Criteria | No existing contract | 4/2/2009 | Answered |
| 10218 | Hydroelectric - Connection | FIT - Northern Hydro Initiative | 4/21/2009 | Answered |
| 10217 | General - Consultation Process | Wall BIPV Solar Energy Systems | 4/2/2009 | Answered |
| 10216 | Hydroelectric - General | Northern Hydro Initiative | 4/21/2009 | Answered |
| 10215 | General - Consultation Process | Access to archived FIT stakeholder meeting audio files | 4/2/2009 | Answered |
| 10214 | Hydroelectric - General | Northern Hydro Initiative | 4/21/2009 | Answered |
| 10213 | General - Consultation Process | Pricing - escalation | 4/2/2009 | Answered |
| 10212 | General - Consultation Process | Section 7.2(e) - economic test | 4/1/2009 | Answered |
| 10211 | General - Consultation Process | 10-day response time | 4/2/2009 | Answered |
| 10210 | General - Consultation Process | Interest on security | 4/1/2009 | Answered |
| 10209 | General - Consultation Process | Parental guarantee as security | 4/2/2009 | Answered |
| 10208 | Hydroelectric - General | Hydro over 50 MW | 4/2/2009 | Answered |
| 10207 | General - Consultation Process | Section 7.2.(e) - Tx cost allocation | 6/3/2009 | Answered |
| 10206 | General - Consultation Process | FIT Reserve & Contract offer | 4/1/2009 | Answered |
| 10205 | Wind - Connection | Economic Test & Tx development | 4/15/2009 | Answered |
| 10204 | Hydroelectric - Eligibility Criteria | Representative stream flow data | 4/3/2009 | Answered |
| 10203 | Hydroelectric - Eligibility Criteria | Section 2.1 (a) (iv). | 4/11/2009 | Answered |
| 10202 | Micro-Generator - General | Connecting Prior to FIT Launch | 4/1/2009 | Answered |
| 10201 | Solar - General | Building permits from City/Municipality for commercial or home rooftops Solar Systems | 4/2/2009 | Answered |
| 10200 | General - Consultation Process | SES 2: Production Line Information | 4/2/2009 | Answered |
| 10199 | General - Consultation Process | SES 2: MOE and MNR coordination | 4/2/2009 | Answered |
| 10198 | Wind - Eligibility Criteria | CIA applications - below the red line | 4/2/2009 | Answered |
| 10197 | Wind - Connection | Connection Capacity | 4/8/2009 | Answered |
| 10196 | Other | Consumer Protection...Bankable Technologies and Installation Processes | 4/1/2009 | Answered |
| 10194 | General - Consultation Process | Unexecuted RESOP Contracts | 4/1/2009 | Answered |
| 10193 | Solar - Eligibility Criteria | Ground Mount Solar and Proximity to Load | 4/2/2009 | Answered |
| 10191 | General - Consultation Process | SES 2: Socialized Costs | 4/2/2009 | Answered |
| 10190 | General - Consultation Process | SES 2: Parameters of Economic Threshold | 4/2/2009 | Answered |
| 10189 | Other | SES 2: Point of Connection | 4/2/2009 | Answered |
| 10188 | Other | SES 2: Production Line | 4/2/2009 | Answered |
| 10187 | Other | SES 2: Process Timelines | 4/2/2009 | Answered |
| 10186 | Other | SES 2: Multiple CIAs | 4/2/2009 | Answered |
| 10185 | Other | SES 2: Renewable Energy Approval | 4/2/2009 | Answered |
| 10184 | General - Consultation Process | SES 2: Early Adopters of rooftop solar | 4/2/2009 | Answered |
| 10183 | Other | SES 2: CIA/SIA | 4/2/2009 | Answered |
| 10182 | General - Consultation Process | SES 2: Energy from Waste | 4/2/2009 | Answered |
| 10181 | General - Consultation Process | SES 2: Former RES Projects | 4/2/2009 | Answered |
| 10180 | General - Consultation Process | application fees fore 250 kW & 500 kW projects | 4/2/2009 | Answered |
| 10179 | Other | SES 2: Expected date of launch | 3/24/2009 | Answered |
| 10177 | General - Consultation Process | SES 1: Targets | 4/8/2009 | Answered |
| 10176 | Other | SES 1: Queue Exempt Facility | 4/2/2009 | Answered |
| 10175 | Other | 4/2/2009 | Answered | |
| 10174 | Other | SES 1: Program Initialization | 4/1/2009 | Answered |
| 10173 | General - Consultation Process | SES 1: Renewable Energy Approval Process | 4/1/2009 | Answered |
| 10172 | Bio-Energy - Eligibility Criteria | SES 1: Clean Energy Opportunities | 4/1/2009 | Answered |
| 10171 | Bio-Energy - Eligibility Criteria | SES 1: Biomass/biogas cogeneration | 4/1/2009 | Answered |
| 10170 | Other | SES 1: Environmental Attributes | 4/1/2009 | Answered |
| 10169 | Solar - Eligibility Criteria | SES 1: Concentrated Solar Power | 4/1/2009 | Answered |
| 10168 | Other | SES 1: Waste Energy Recovery | 4/1/2009 | Answered |
| 10167 | Other | SES 1: When is price applied | 4/1/2009 | Answered |
| 10166 | Other | SES 1: Clean Energy and First Nations | 4/2/2009 | Answered |
| 10165 | Other | SES 1: Old Orange Zones | 4/2/2009 | Answered |
| 10164 | Solar - Contract Pricing | SES 1: OPA assumptions for Pricing | 4/2/2009 | Answered |
| 10162 | Micro-Generator - General | SES 1: GST/PST refunds | 4/1/2009 | Answered |
| 10161 | Other | SES 1: Timelines | 4/1/2009 | Answered |
| 10160 | Other | SES 1: Cogeneration | 4/2/2009 | Answered |
| 10159 | Other | SES 1: Purpose of Application Security Fee? | 4/2/2009 | Answered |
| 10158 | Solar - Contract Pricing | SES 1: Price reduction | 4/2/2009 | Answered |
| 10156 | Other | SES 1: Shovel ready projects | 4/11/2009 | Answered |
| 10155 | General - Consultation Process | Connection outside FIT | 4/15/2009 | Answered |
| 10154 | General - Consultation Process | How to appeal not offering FIT pricing to existing Standard Offer Contract Holders? | 4/2/2009 | Answered |
| 10153 | General - Consultation Process | 4/2/2009 | Answered | |
| 10152 | Solar - Contract Pricing | Small Scale Solar Ground Mount | 4/1/2009 | Answered |
| 10150 | Solar - Eligibility Criteria | SES 1: Security | 4/2/2009 | Answered |
| 10149 | Solar - Contract Pricing | SES 1: Degression | 4/2/2009 | Answered |
| 10148 | Other | Application Fee | 3/24/2009 | Answered |
| 10147 | General - Consultation Process | SES 1: Program Initialization Period | 4/2/2009 | Answered |
| 10146 | Micro-Generator - General | SES 1: Technological Innovation | 4/11/2009 | Answered |
| 10145 | General - Consultation Process | SES 1: Legacy projects | 4/2/2009 | Answered |
| 10144 | Other | SES 1: Hybrid | 4/11/2009 | Answered |
| 10143 | Wind - Eligibility Criteria | SES 1: Met tower and data collection | 4/2/2009 | Answered |
| 10142 | General - Consultation Process | SES 1: Incremental | 3/27/2009 | Answered |
| 10141 | Other | SES 1: Geothermal | 3/27/2009 | Answered |
| 10140 | Other | SES 1: Rates | 4/1/2009 | Answered |
| 10139 | Bio-Energy - Eligibility Criteria | SES 1: Wood from construction | 3/27/2009 | Answered |
| 10138 | Other | SES 1: Projects off grid - conservation | 4/11/2009 | Answered |
| 10137 | Solar - Contract Pricing | SES 1: Degression | 3/27/2009 | Answered |
| 10136 | Other | SES 1: Hybrid Systems | 3/27/2009 | Answered |
| 10135 | Other | SES 1: Municipal ownership | 3/27/2009 | Answered |
| 10134 | Other | SES 1: Distribution Companies | 3/27/2009 | Answered |
| 10133 | Micro-Generator - General | SES 1: Selling house with solar panels | 3/27/2009 | Answered |
| 10132 | Other | SES 1: Attributes including ecoEnergy | 3/27/2009 | Answered |
| 10131 | General - Consultation Process | What is the logic behind securities? | 4/11/2009 | Answered |
| 10130 | Other | Eligibility of Geothermal for Electricity Production | 4/2/2009 | Answered |
| 10129 | Solar - General | The application process for REFIT - For homeowners | 3/27/2009 | Answered |
| 10128 | General - Consultation Process | Application submission time | 4/2/2009 | Answered |
| 10127 | Solar - General | Net Metering Connection | 3/31/2009 | Answered |
| 10126 | Solar - General | Gross Nameplate Capacity | 4/2/2009 | Answered |
| 10125 | Solar - Contract Pricing | Price degression for ground mounted systems | 4/1/2009 | Answered |
| 10124 | Solar - General | Provincial Content | 4/2/2009 | Answered |
| 10123 | General - Consultation Process | Solar -- rooftop mount | 3/27/2009 | Answered |
| 10121 | Solar - General | For Legacy projects, $15,000 vaporized? | 4/2/2009 | Answered |
| 10120 | General - Consultation Process | SES 1: European FIT | 3/30/2009 | Answered |
| 10119 | Micro-Generator - General | SES 1: Home REFIT Rules | 3/23/2009 | Answered |
| 10118 | General - Consultation Process | SES 1: Legacy Projects and CIA | 3/23/2009 | Answered |
| 10117 | General - Consultation Process | SES 1: Renewable Energy Facilitator | 3/23/2009 | Answered |
| 10116 | General - Consultation Process | SES 1: Funding of upgrades? | 3/23/2009 | Answered |
| 10115 | General - Consultation Process | SES 1: Kyoto guidelines | 3/30/2009 | Answered |
| 10114 | General - Consultation Process | Ses 1: Legacy project cutoff | 3/23/2009 | Answered |
| 10113 | General - Consultation Process | SES 1: Expansions and upgrades | 3/23/2009 | Answered |
| 10112 | General - Consultation Process | SES 1: Cost sharing | 3/23/2009 | Answered |
| 10111 | General - Consultation Process | SES 1: Connection costs | 3/23/2009 | Answered |
| 10110 | General - Consultation Process | SES 1: Provincial Content | 4/1/2009 | Answered |
| 10108 | Solar - General | Change in time frame for Solar Farm installation from 3 to 2 years. | 4/1/2009 | Answered |
| 10107 | Micro-Generator - General | SES 1: Micro-wind allowed | 3/30/2009 | Answered |
| 10105 | General - Consultation Process | CIA's honoured | 3/23/2009 | Answered |
| 10104 | Solar - General | CIA, CCA, CCRA | 3/24/2009 | Answered |
| 10103 | Solar - Contract Pricing | 10kW micros | 4/2/2009 | Answered |
| 10102 | General - Consultation Process | How do we get "Recaptured Energy" qualified for FIT? | 3/24/2009 | Answered |
| 10101 | General - Consultation Process | Legacy Projects, Queue and Initilization Period | 4/1/2009 | Answered |
| 10100 | Wind - Connection | CCRA Timeline for Legacy Projects | 4/15/2009 | Answered |
| 10099 | Solar - General | 3/23/2009 | Answered | |
| 10098 | Solar - General | Ground Mount Solar Systems | 3/20/2009 | Answered |
| 10097 | Solar - General | What Are House REFIT Rule? | 3/23/2009 | Answered |
| 10096 | Solar - General | Standard Offer Program | 3/20/2009 | Answered |
| 10094 | Bio-Energy - Connection | Interconnection - Shallow vs Deep Cost Allocation | 3/20/2009 | Answered |
| 10093 | General - Consultation Process | Completion and Performance Security | 3/23/2009 | Answered |
| 10092 | Wind - Eligibility Criteria | Aggregation of CIA | 3/20/2009 | Answered |
| 10091 | General - Consultation Process | Clarification of Section 11.2(c) | 4/2/2009 | Answered |
| 10090 | General - Consultation Process | RESOP vs FIT for rooftop solar | 3/20/2009 | Answered |
| 10089 | General - Consultation Process | Economic Connection Test | 3/27/2009 | Answered |
| 10088 | General - Consultation Process | Starting date of 20-year agreement | 3/20/2009 | Answered |
| 10087 | Other | Municipal Taxes | 3/23/2009 | Answered |
| 10086 | Other | Evaluation of Property Value | 3/20/2009 | Answered |
| 10084 | General - Consultation Process | Northwestern orange zone | 3/20/2009 | Answered |
| 10083 | General - Consultation Process | Solar Farm installation deadline from 3 to 2 years! | 3/27/2009 | Answered |
| 10082 | General - Consultation Process | Renewable Energy Approval requirements | 3/20/2009 | Answered |
| 10081 | Solar - Eligibility Criteria | Residential REFIT Rules | 3/23/2009 | Answered |
| 10080 | Solar - Eligibility Criteria | Net Metering | 3/24/2009 | Answered |
| 10079 | General - Consultation Process | Hydro One Applications List | 4/11/2009 | Answered |
| 10078 | General - Consultation Process | CONNECTION RESOURCE DATABASE | 3/20/2009 | Answered |
| 10077 | Solar - General | Duration of Solar Contract | 3/20/2009 | Answered |
| 10076 | Wind - Eligibility Criteria | Legacy Projects | 3/20/2009 | Answered |
| 10075 | Solar - Contract Pricing | Rate Reduction Beyond 100 MW | 3/20/2009 | Answered |
| 10074 | Solar - Contract Pricing | APPLICATION SECURITY vs. COMPLETION SECURITY | 3/20/2009 | Answered |
| 10073 | Other | Manufacturing Incentives | 3/23/2009 | Answered |
| 10072 | General - Consultation Process | SES 1: RESOP Pricing | 3/20/2009 | Answered |
| 10071 | General - Consultation Process | SES 1: Completion and Performance Security | 3/23/2009 | Answered |
| 10070 | Other | SES 1: CHP III | 3/20/2009 | Answered |
| 10069 | Other | SES 1: Provincial Content | 3/23/2009 | Answered |
| 10068 | Micro-Generator - General | SES 1: Apply now | 3/24/2009 | Answered |
| 10067 | General - Consultation Process | SES 1: Targets | 3/20/2009 | Answered |
| 10066 | General - Consultation Process | SES 1: Proposed FIT Pricing | 3/20/2009 | Answered |
| 10065 | Other | SES 1: RESOP contracts | 3/20/2009 | Answered |
| 10064 | Other | SES 1: Legacy projects | 3/20/2009 | Answered |
| 10063 | Wind - Contract Pricing | SES 1: Pricing for micro-wind | 3/20/2009 | Answered |
| 10062 | Micro-Generator - General | SES 1: Micro-scale ground-mounted PV | 3/20/2009 | Answered |
| 10061 | Solar - Contract Pricing | SES 1: Price for 10kW size | 3/20/2009 | Answered |
| 10060 | Other | SES 1: Interconnection costs | 3/20/2009 | Answered |
| 10059 | Other | SES 1: Zoning in Oak Ridge Moraine & Green Belt | 3/20/2009 | Answered |
| 10058 | General - Consultation Process | Qualifying Recaptured Energy | 3/20/2009 | Answered |
| 10057 | General - Consultation Process | Price Schedule | 3/23/2009 | Answered |
| 10056 | General - Consultation Process | Attending Tuesday Consultations | 3/20/2009 | Answered |
| 10055 | Wind - Eligibility Criteria | Impact of MNR delay in securing Applicant of Record | 3/23/2009 | Answered |
| 10054 | Bio-Energy - Connection | Connection Cost Allocation | 3/20/2009 | Answered |
| 10053 | General - Consultation Process | Qualifying Recaptured Energy | 3/20/2009 | Answered |
| 10052 | Wind - General | local content | 3/20/2009 | Answered |
| 10051 | Solar - Contract Pricing | BIPV under 10 kW | 4/2/2009 | Answered |
| 10050 | General - Consultation Process | Wind Assessment | 3/20/2009 | Answered |
| 10049 | Other | Audit | 3/20/2009 | Answered |
| 10048 | General - Consultation Process | Eligible Aboriginal Projects | 4/2/2009 | Answered |
| 10046 | Solar - Contract Pricing | 3/20/2009 | Answered | |
| 10045 | Wind - Eligibility Criteria | Provisions for local content | 3/20/2009 | Answered |
| 10044 | General - Consultation Process | Environmental commissioner | 3/19/2009 | Answered |
| 10042 | Micro-Generator - General | Existing RESOP not transferred to FIT | 3/20/2009 | Answered |
| 10041 | Wind - Contract Pricing | follow up onshore v. offshore wind | 3/20/2009 | Answered |
| 10040 | General - Consultation Process | Micro-Wind | 3/20/2009 | Answered |
| 10039 | Solar - General | Ground Mount Pricing | 3/23/2009 | Answered |
| 10038 | Micro-Generator - General | Draft Program Rules - Multiple Energy Sources | 3/25/2009 | Answered |
| 10035 | Solar - Eligibility Criteria | Pending solar projects | 3/20/2009 | Answered |
| 10034 | Solar - Eligibility Criteria | Solar < 10 kW | 3/20/2009 | Answered |
| 10033 | General - Consultation Process | RESOP vs FIT | 3/20/2009 | Answered |
| 10032 | General - Consultation Process | Northern Region constraints? | 3/20/2009 | Answered |
| 10031 | Solar - Connection | metering | 3/20/2009 | Answered |
| 10030 | Solar - Contract Pricing | FiT Consistancy for small Community Based Solar Systems | 3/20/2009 | Answered |
| 10029 | Solar - General | leasing someone's rooftop for putting a Solar project | 3/20/2009 | Answered |
| 10028 | Solar - Contract Pricing | 100 kW FIT | 4/2/2009 | Answered |
| 10027 | General - Consultation Process | Key Contacts at OPA | 3/20/2009 | Answered |
| 10026 | Solar - Contract Pricing | 9% Degression of Solar PV - Clarification | 3/20/2009 | Answered |
| 10025 | Wind - Contract Pricing | Big difference between Solar vs. Wind FIT prices | 3/20/2009 | Answered |
| 10024 | Solar - Eligibility Criteria | Parking lot structure PV mounts | 3/20/2009 | Answered |
| 10023 | General - Consultation Process | FIT for Clean Energy Projects | 3/16/2009 | Answered |
| 10022 | Bio-Energy - Connection | Hydro One CCRA Qualification under FIT | 3/20/2009 | Answered |
| 10021 | General - Consultation Process | Contract Requirements | 3/20/2009 | Answered |
| 10020 | General - Consultation Process | Current RESOP Contracts | 3/19/2009 | Answered |
| 10019 | General - Consultation Process | POWER HOST | 3/16/2009 | Answered |
| 10018 | General - Consultation Process | carbon credits | 3/19/2009 | Answered |
| 10017 | General - Consultation Process | Ground mounted Solar PV & Water Power | 3/16/2009 | Answered |
| 10016 | Other | Status of current RESOP Applicants | 4/2/2009 | Answered |
| 10015 | Wind - Contract Pricing | Onshore v offshore wind | 3/16/2009 | Answered |
| 10014 | General - Consultation Process | Exclusion of Energy modes | 4/2/2009 | Answered |
| 10013 | General - Consultation Process | Publication of background information | 3/20/2009 | Answered |
| 10012 | General - Consultation Process | Ground mounted PV | 3/20/2009 | Answered |
| 10011 | General - Consultation Process | Existing Projects Eligible for New FIT rates | 3/20/2009 | Answered |
| 10010 | Bio-Energy - Contract Pricing | Inflation adjustment | 4/2/2009 | Answered |
| 10009 | Solar - Contract Pricing | FIT pricing for current RESOPs | 3/16/2009 | Answered |
| 10008 | Solar - Contract Pricing | Application of new FIT rates to existing RESOP SOCs | 4/2/2009 | Answered |
| 10007 | General - Consultation Process | CIA Queue positon | 3/16/2009 | Answered |