Prerequisites

You will have to request a notice to proceed from the OPA once you have completed and obtained the required approvals and permits. Your notice to proceed request must include:

  • a copy of your impact assessment(s) as applicable
    • connection impact assessment
    • system impact assessment
    • customer impact assessment
  • a copy of your renewable energy approval
  • domestic content plan
  • financing plan.

Further details can be found in the FIT contract.