The following table sets out key FIT contract payments and timelines. Please refer to the FIT contract for more details about these provisions.
| FIT Contract | On-shore wind | Off-shore wind | Solar PV | Waterpower | Bioenergy |
| Milestone date for commercial operation | three years | four years | three years | five years | three years |
| Notice to proceed response date | 15 months | 15 months | 15 months | 24 months | 15 months |
| Notice to proceed daily delay amount | $0.033/kW | $0.067/kW | $0.033/kW | $0.067/kW | $0.067/kW |
| Pre-construction liability limit |
$400,000 + $2.00/kW |
$500,000 + $2.00/kW |
$250,000 + $10.00/kW |
$500,000 + $20.00/kW |
$400,000 + $2.00/kW |
| First completion and performance security (initial security) | $20/kW | $20/kW | $50/kW | $20/kW | $20/kW |
| Second completion and performance security (incremental NTP security) | $10/kW | $10/kW | $25/kW | $10/kW | $10/kW |
Note: Aboriginal and community projects have a lower security amount of $5/kW.