Overview

There are three steps to submit a FIT Program application:

  1. Register for the FIT Program.
  2. Submit your application online - the OPA will send you a confirmation email and a reference number specific to your application.
  3. Submit your application package by mail to the OPA within five business days.

The application package must include:

  • two paper copies: one original prominently marked "Original" and one additional copy
  • application fee
  • application security (if applicable)
  • authorization letter (Exhibit A)
  • evidence of land access rights
  • evidence that the agricultural land restrictions have been met (applicable to ground-mounted solar PV projects greater than 100 kW).

More details on the required application materials listed above can be found here .