There are three steps to submit a FIT Program application:
-
Register for the FIT Program.
-
Submit your application online - the OPA will send you a confirmation email and a reference number specific to your application.
-
Submit your application package by mail to the OPA within five business days.
The application package must include:
-
two paper copies: one original prominently marked "Original" and one additional copy
-
application fee
-
application security (if applicable)
-
authorization letter (Exhibit A)
-
evidence of land access rights
-
evidence that the agricultural land restrictions have been met (applicable to ground-mounted solar PV projects greater than 100 kW).
More details on the required application materials listed above can be found here .