The OPA has made a rule change for capacity allocation exempt (CAE) FIT applications submitted on or after December 8, 2010. A new eligibility criterion has been added that requires CAE facilities to be deemed by the OPA as capable of connecting at the proposed connection point. To access the new version of the FIT Rules, please click here.
This rule change is designed to ensure that potential connection issues are identified as early as possible in the application and contracting processes and will better align projects with available connection capacity.
The proposed rule change was posted for comment on December 8, 2010. The comment period closed on January 7, 2011. We thank all those who made submissions.
Based on feedback received, the OPA will require CAE FIT applicants to obtain a Connection Impact Assessment from their local distribution company after the OPA issues a contract. This is consistent with the FIT Program process for larger projects and ensures fairness in terms of access to the grid. To view the Guidelines for Connection Capability, click here.
For more information about connecting your CAE FIT project, please speak to your local distribution company. If you have further questions, you can contact the OPA at 1-888-387-3403 or send an email to fit@powerauthority.on.ca.