- What are the domestic content requirements?
- How do the domestic content requirements work? - Are there domestic content requirements for microFIT projects? - What is the definition of domestic content from the program rules? - Are projects with RESOP or other OPA contracts eligible to transition to FIT and/or microFIT and do they have to meet the domestic content rules? - What if my project was installed after the introduction of the Green Energy and Green Economy Act but before the launch of the FIT Program - do I have to meet the domestic content rules? Developers will be required to have a certain percentage of their project costs come from Ontario goods and labour at the time they reach commercial operation.
The percentage requirements are assessed on the total project cost. If designated activities are done in Ontario, developers receive a qualifying percentage towards their domestic content requirement. Criteria for designated activities range from manufacturing certain components in Ontario to retaining labour and consulting services provided by Ontario residents. Developers will be required to have a certain percentage of their project costs come from Ontario goods and labour at the time they reach commercial operation.
The definition of "domestic content" is in Section 6.4 (a) of the FIT Program Rules as follows: (a) The FIT Contract will require that Contract Facilities utilizing windpower with a Contract Capacity greater than 10 kW, or Contract Facilities utilizing solar (PV), achieve a minimum percentage for their Domestic Content Level, which will be set out on the FIT Contract Cover Page (the "Minimum Required Domestic Content Level"). (i) For windpower Projects with a Contract Capacity greater than 10 kW, the Minimum Required Domestic Content Level is 25% for FIT Contracts that have a Milestone Date For Commercial Operation prior to January 1, 2012 and 50% for FIT Contracts that have a Milestone Date For Commercial Operation on or after January 1, 2012. (ii) For solar (PV) Projects with a Contract Capacity greater than 10 kW, the Minimum Required Domestic Content Level is 50% for FIT Contracts that have a Milestone Date for Commercial Operation prior to January 1, 2011 and 60% for FIT Contracts that have a Milestone Date For Commercial Operation on or after January 1, 2011. (iii) For solar (PV) Projects with a Contract Capacity less than or equal to 10 kW, the Minimum Required Domestic Content Level is 40% for FIT Contracts that have a Milestone Date for Commercial Operation prior to January 1, 2011 and 60% for FIT Contracts that have a Milestone Date For Commercial Operation on or after January 1, 2011. Are projects with RESOP or other OPA contracts eligible to transition to FIT and/or microFIT and do they have to meet the domestic content rules?
Projects of any renewable technology that have a capacity of 500 kW or less and were purchased or were in service by 11:59 p.m. on October 1, 2009 will be eligible to transition to the FIT and microFIT Programs. They will be deemed to have met the domestic content requirements. Generators who have not been operating under an OPA contract will receive a 20-year FIT or microFIT contract. Generators who have been operating under a RESOP contract will obtain a contract representing the balance of the 20-year FIT or microFIT contract. For more details, please refer to the Transition Options FAQs or the Transition Options webpage. What if my project was installed after the introduction of the Green Energy and Green Economy Act but before the launch of the FIT Program - do I have to meet the domestic content rules?
Renewable energy projects that are installed following the introduction of the Green Energy and Green Economy Act will be eligible to participate in the FIT Program, provided they meet the eligibility requirements, including requirements for domestic content. |
Search
Key Documents
FIT Price Schedule
August 13, 2010 FIT Rules August 13, 2010 FIT Prescribed Forms August 11, 2010 FIT Multiple Project Guidelines August 4, 2010 FIT Contract July 2, 2010 FIT Rules July 2, 2010 Standard Definitions July 2, 2010 FIT Application Form Dec. 1, 2009 FIT Program Overview July 2, 2010 Programme de TRG – Aperçu July 2, 2010 What's New
August 13, 2010
FIT Price Schedule August 13, 2010 FIT Rules August 11, 2010 Updated FIT prescribed forms August 4, 2010 Updated FIT guidelines for multiple projects on one property July 2, 2010 Updated Rules, contract, definitions and overview posted in Program Resources June 1, 2010 FIT Program Timeline May 28, 2010 OPA receives response from Measurement Canada to proposal to address in-series connection configurations May 19, 2010 Behind-the-meter facilities no longer permitted under FIT Program May 10, 2010 New Ontario Program Will Help Communities Develop Clean Energy Projects May 7, 2010 More Clean Energy Being Produced in Ontario Upcoming Events
|